Print Edition – 4.14.16
R
Reporter · April 14, 2016




Gov. Kathy Hochul's executive order pausing state environmental permits for large data centers has stalled a privately funded $1.5 billion AI campus planned for Niagara Falls, a site with existing hydropower and grid capacity. The article argues the state should review the project promptly and decide it on its merits r

Niagara Falls Redevelopment, owned by the Milstein family, wants to build a $1.5 billion Niagara Digital Campus with nine data center buildings on vacant South End land, betting the city can again lean on the Niagara River's cheap power. A consultant's study projects 550 permanent jobs and $414.9 million in taxes over